Payment Claims and Payment Schedules in Victoria: What Builders and Subbies Need to Know After the 2026 Changes
Updated: Nov 15
By Rami Rajkumar, CPA, Founder, TechEdge Accounting. Published 4 November 2026. Updated 10 November 2026.
In short. In Victoria, the Building and Construction Industry Security of Payment Act 2002 gives anyone who does construction work or supplies goods and services for it a fast way to get paid. You serve a payment claim. The other side has 10 business days to pay or serve a payment schedule. If they do neither, they owe the full amount. The rules changed on 15 April 2026, and the changes apply to contracts signed before that date too. This guide covers what changed, the deadlines, and the records that make a claim stick.
Who does the Security of Payment Act cover in Victoria?
The Act covers most building work and related supplies in Victoria: head contractors, subcontractors, suppliers and consultants. The main exception is a domestic building contract between a builder and a home owner, which falls under the Domestic Building Contracts Act 1995. The builder's contracts with its own subbies and suppliers on that home are still covered.
"Pay when paid" and "pay if paid" clauses have no effect under the Act. The 2026 changes went further and also restrict clauses that make payment depend on another contract.
What changed on 15 April 2026?
The Building Legislation Amendment (Fairer Payments on Jobsites and Other Matters) Act 2025 made the biggest changes to the Victorian scheme in years. They started on 15 April 2026 and apply to construction contracts entered into before, on or after that date. The old rules still apply to a payment claim served before 15 April 2026 and to an adjudication applied for but not decided by then.
The changes that matter most for cash flow:
Claimable variations and excluded amounts are gone. Victoria used to restrict what you could put in a claim. Those restrictions have been removed.
Monthly claims. A claim can be served from the last day of each month in which you did work or supplied goods, or an earlier date if the contract allows. Only one claim a month.
More time to claim after you finish. The final deadline is the day before six months after practical completion (or after you supply the last goods or services), unless the contract gives a later date. It used to be three months.
A cap on payment terms. A contract can't make a progress payment due later than 20 business days after the claim is served. Longer terms have no effect. If the contract is silent, a default of 10 business days applies.
Christmas doesn't count. 22 December to 10 January is not counted as business days for the Act's timeframes.
Performance security. You can now claim the release of a bank guarantee or other security, as well as progress payments.
What must a payment claim include?
A payment claim must:
identify the construction work done, or the goods and services supplied
state the amount claimed
state that it is made under the Building and Construction Industry Security of Payment Act 2002
Miss the third line and you have an ordinary invoice, not a claim under the Act. Put it on every claim template you use.
What must a payment schedule include?
If you receive a claim and don't agree with the full amount, you serve a payment schedule within 10 business days, or sooner if the contract says so. It must:
identify the payment claim it relates to
state the amount (if any) you propose to pay
give every reason why that amount is less than the claim
Be thorough. Under the 2026 changes, a respondent can't rely in adjudication on reasons it left out of the schedule.
If you miss the 10 business days and don't pay, you become liable for the full amount claimed.
What can you do if you're not paid?
The claimant has three options:
Adjudication. Apply through an Authorised Nominating Authority, not to the Building and Plumbing Commission. If the schedule is less than the claim, apply within 10 business days of receiving the schedule. If the scheduled amount isn't paid when due, apply within 10 business days of the due date. If there was no schedule and no payment, first give notice of your intention to apply within 10 business days of the due date. The respondent then has 5 business days to serve a schedule (it used to be 2).
Court. Recover the unpaid amount in the Magistrates', County or Supreme Court, depending on how much is owed.
Suspend work. Give three business days' written notice that says it's made under the Act.
Adjudicators must now decide within 10 business days of appointment, or of the last day for the respondent's response if that's later. The parties can agree to extend that by up to 20 business days. Review adjudications have been abolished.
Example: a subbie's month
A Victorian electrical subcontractor finishes October's work on a commercial fit out. The contract lets them claim on the last day of the month and pays 20 business days after a claim.
Last day of the month: serve the October claim for $86,400, stating it's made under the Act
Within 10 business days: the head contractor must pay or serve a schedule. It schedules $71,000 and lists two reasons.
Within 10 business days of receiving that schedule: the subbie can apply for adjudication on the $15,400 gap, or accept it
20 business days after the claim: the $71,000 is due. If it isn't paid, the subbie has 10 business days from the due date to apply for adjudication.
This is an illustration, not a real client. Count the days with the Act's definition of business days, and check your own contract.
The bookkeeping that wins claims
Adjudicators decide on the papers, quickly. The business with the cleaner records usually does better. What we set up for clients:
A claim register. Every claim, the date and method of service, the amount, the due date, and the schedule date, with the 10 business day deadline worked out the day the claim goes out.
Claims built from the job cost ledger. Each claim ties to the work done in the month, so the amount can be backed up line by line.
Variations logged as they happen. Instructions, dates and costs recorded when the work is done, not reconstructed at claim time.
Schedules answered in writing, on time. If you're the head contractor, every claim that lands gets a schedule or a payment inside 10 business days, with reasons written into the schedule.
Retentions and securities tracked to their release dates. See our guide to retention money trust rules by state.
A Christmas calendar. With 22 December to 10 January excluded, deadlines that would have fallen over the break move. Plan the December claim and your shutdown cash plan together.
We are accountants, not lawyers. We keep the records and deadlines that make a claim easy to prove. For advice on a dispute or a contract, speak to a construction lawyer.
Payment claims and schedules: quick answers
How long do you have to respond to a payment claim in Victoria?
10 business days after the claim is served, or less if the contract says so. You either pay the full amount or serve a payment schedule. 22 December to 10 January doesn't count as business days under the Act.
What happens if you don't serve a payment schedule?
If you don't serve a schedule within 10 business days and don't pay, you become liable for the full amount claimed. The claimant can then go to court for it, or give notice and apply for adjudication.
How often can you make a payment claim?
Once a month. A claim can be served from the last day of each month in which you did work or supplied goods, or an earlier date if the contract allows.
When does a progress payment have to be paid?
No later than 20 business days after the claim is served. Longer payment terms have no effect, and if the contract is silent a default of 10 business days applies.
Is an invoice the same as a payment claim?
Not unless it says it's made under the Building and Construction Industry Security of Payment Act 2002. It also has to identify the work or supplies and state the amount. Without that statement it's an ordinary invoice.
Does the Act cover home renovations?
A domestic building contract between a builder and a home owner isn't covered. That falls under the Domestic Building Contracts Act 1995. The builder's contracts with its own subbies and suppliers on that job still are.
Related reading
Want this handled for you each month? See how our construction bookkeeping works for builders and subcontractors.
This article is general information only and isn't legal, financial or tax advice. It's based on the Building and Plumbing Commission's Security of Payment guidance (overview, changes to the SOP scheme, transitional arrangements, responding to a payment claim, options if a respondent doesn't pay, and SOP adjudication) as at 4 November 2026. Check the current Act on legislation.vic.gov.au or speak to a construction lawyer before acting.
Talk to a CPA
TechEdge is a CPA-led outsourced finance team for Australian construction, EPC, solar and property businesses.
Book a free 30-minute call with a CPA, email info@techedgeaccounting.com.au or call +61 468 634 973.

Comments